2016-01-18 - 24194 - Service Request - 2016 Supply Chain and Finance - Week ending April 15 #ProductionBreakFix #MMFI #FIMMSD
2016-01-18 - 24194 - Service Request - Supply Chain and Finance
Problem Summary
All supporting activities pertaining to SCM-FI that are less than 4 hours in 2016 are updated in this sheet.
Admin Info
Purpose
|
All supporting activities that are less than 4 hours in 2016 are updated in this sheet.
|
Requested by
|
Jeffrey Mau
|
Issue Date
|
04-11-2016 to 04-15-2016
|
Resolved by
|
Adithya/Laxman/Thiyagu/Raghav
|
Document Status
|
Completed
|
Detailed Problem Description
(Include Screen Shots if required )
1. 04-11-2016 to 04-14-2016
LIDS Safety Stock
2. 04-11-2016 to 04-14-2016
ZHOT Transaction Changes.
3. 04-14-2016
PO 4500149779, Issue while deleting the confirmations in PO.
4. 04-15-2016
MSRP Value in PO Download file SNC
Solution Analysis and Recommendations
(Include Screen Shots if required)
1. Discussion carried out on LIDS Safety stock requirement and proposed solutions, created a document and sent to NE.
2. Created a spec document on the changes and attended meeting on the ZHOT Changes and gathered additional requirements.
3. The error which was showing when deleting the confirmations in the PO was a warning message and could be able to delete the confirmations.
4. Analysis carried out on PO Download file SNC. Understand that the MSRP Value is displayed wrong in PO Feed file also.
SCM - Adithya-Venkat - 2016-04-15 - 26604 - Spec - Make changes to MSRP data in SNC (Bhumi by 2016-04-28)
Resolution
1. Sent the proposal document to NE.
2. Prepare a updated spec document and send to NE.
3. e Mail has been sent to NE that that is a warning message and ignore it and save the PO.
4. Analysis carried out for the reason and sent the estimate required for the changes.
Release Information
Provide link here to Release Notes if Technical Objects were changed