2016-01-18 - 24194 - Service Request - 2016 Supply Chain and Finance - Week ending April 15 #ProductionBreakFix #MMFI #FIMMSD

2016-01-18 - 24194 - Service Request - Supply Chain and Finance

Problem Summary


All supporting activities pertaining to SCM-FI that are less than 4 hours in 2016 are updated in this sheet.

Admin Info



Purpose
All supporting activities that are less than 4 hours in 2016 are updated in this sheet.
Requested by
Jeffrey Mau
Issue Date
04-11-2016 to 04-15-2016
Resolved by
Adithya/Laxman/Thiyagu/Raghav
Document Status
Completed

Detailed Problem Description

(Include Screen Shots if required )

1. 04-11-2016 to 04-14-2016 LIDS Safety Stock
2. 04-11-2016 to 04-14-2016 ZHOT Transaction Changes.
3. 04-14-2016 PO 4500149779, Issue while deleting the confirmations in PO.
4. 04-15-2016 MSRP Value in PO Download file SNC

Solution Analysis and Recommendations

(Include Screen Shots if required)


1. Discussion carried out on LIDS Safety stock requirement and proposed solutions, created a document and sent to NE.
2. Created a spec document on the changes and attended meeting on the ZHOT Changes and gathered additional requirements.
3. The error which was showing when deleting the confirmations in the PO was a warning message and could be able to delete the confirmations.
4. Analysis carried out on PO Download file SNC. Understand that the MSRP Value is displayed wrong in PO Feed file also.
SCM - Adithya-Venkat - 2016-04-15 - 26604 - Spec - Make changes to MSRP data in SNC (Bhumi by 2016-04-28)

Resolution


1. Sent the proposal document to NE.
2. Prepare a updated spec document and send to NE.
3. e Mail has been sent to NE that that is a warning message and ignore it and save the PO.
4. Analysis carried out for the reason and sent the estimate required for the changes.


Release Information